General procurement guidance; not a project-specific design approval.
Make receipt inspection match the purchase order
A delivery check is useful when it links each received bundle or sheet to the approved quotation, order, drawing and documents. The check should record what arrived and any visible difference from the agreed requirements. It does not create new tolerances or prove long-term material suitability.
This checklist applies to industrial thermoplastic sheet orders. Xin Longdi’s product pages cover its PP, PPH, HDPE, PVC and PVDF sheet offerings. The specified grade, dimensions, tolerances, documents, packing and inspection scope remain the ones agreed for the individual order. Use the Purchasing Guide for existing commercial information.
Prepare the receiving team before dispatch
Ask the supplier to make the shipment identifiable against the order. Agree how bundles or packages will be marked, how the packing list maps to order line items, and which records will accompany the delivery. If an item has a drawing revision, part number, surface requirement or special document request, define how the receiving team can match it to the package.
Before arrival, give the receiving team the current purchase specification and arrange a suitable place to photograph and inspect the shipment. Confirm who should be contacted if the quantity, labels or condition do not match the agreed documents. If the project requires inspection before unloading or unpacking, assign that responsibility in advance.
Record the package condition before unpacking
At delivery, record the date, carrier or shipment reference, package identifier and visible condition. Photograph damaged packaging before it is removed, including the affected item label where possible. Keep images linked to the relevant order line rather than saving an unlabeled set of warehouse photographs.
Then compare the received count and package marks with the packing list and purchase order. Note missing packages, incorrect labels, mixed bundles, wet or torn wrapping, impact marks and any other visible concern. These are observations for review; they do not, by themselves, identify the cause or determine whether the sheet is acceptable.
Use agreed handling and lifting instructions for the load. Do not drag sheet faces across each other or remove protective film in a way that could create damage. Where the contract specifies how and when packaging should be opened, follow that instruction and document any condition that was already visible on arrival.
Check identity, quantity and documents
For each order line, reconcile:
- Supplier and purchase-order reference.
- Product description and material designation shown on the approved order.
- Package or item marks and any batch or lot references supplied.
- Number of sheets or parts received against the packing list.
- Dimensions and tolerances required by the order, using the agreed measurement method.
- Requested material, inspection or compliance documents and their stated product or batch scope.
- Surface, protective-film and packaging requirements written into the purchase specification.
A label, certificate or data sheet should be read for the item and scope it actually identifies. If a requested document is missing or describes another product, record the discrepancy and ask the supplier to clarify it. Do not treat colour or appearance as a grade identification, and do not use a general catalogue value as an order tolerance.
Inspect visible condition against agreed criteria
Inspect the surfaces and edges for damage relevant to the agreed acceptance criteria. Record the location and extent of any visible mark, crack, dent, deformation or contamination, and whether it is on a protected surface or an exposed edge. Do not invent a pass/fail threshold after the shipment arrives. Compare observations with the purchase specification, approved sample or inspection plan if one was agreed.
Measure only the features and sample size defined for the order. Record the instrument, method, location and result in the form used by the project. If no inspection method or tolerance was agreed, ask the responsible buyer or engineer to decide how to resolve the uncertainty before releasing the material for fabrication.
Document a discrepancy and hold the affected item for review
A practical receiving record should capture:
- Purchase order and line reference, including the item number.
- Package or sheet identity, including its label and any supplied batch reference.
- Check performed: count, document review, visual check or agreed measurement.
- Specific observation against the order or visible condition.
- Evidence reference, such as a photograph or inspection record.
- Immediate action, such as protected, awaiting clarification or released.
- Person responsible for the disposition: buyer, supplier, project engineer or quality reviewer.
If there is a discrepancy, identify the affected quantity, protect it from further handling and send the supplier the order reference, photographs and specific question. Keep the package labels and related documents with the record. Obtain a documented disposition before mixing uncertain material into accepted stock or beginning work that could make the issue harder to assess.
Close the receiving record before fabrication
When the delivery matches the order, record who completed the checks and where the material was placed for storage. Link the documents to the order and retain any agreed inspection evidence for the project file. If an exception remains open, mark it clearly so purchasing, fabrication and engineering teams do not mistake an unresolved item for approved material.
For future orders, use the discrepancy to clarify the packing, marking or acceptance clause before dispatch. This creates a more useful receiving process without assuming one universal inspection standard for every plastic, product form or application.
Send delivery and inspection needs with the quotation request
State the delivery destination, unloading limitations, package identification needs, surface protection and any inspection or documentation requirements when requesting a price. Identify which requirements are mandatory and which need supplier confirmation. The supplier can then state what its offer includes and flag any condition that needs agreement.
Use the plastic sheet inquiry to send the material, dimensions, quantity, destination and receiving requirements. For material identity questions, review the material document hub and request records for the exact quoted product and order.